A deadly train crash in the southern state of Oaxaca has resulted in the deaths of at least 13 people, an incident likely to revive censure from critics regarding the speed and handling of the country's flagship government projects.
The disaster occurred on the trans-isthmus railway, a line constructed to link the Atlantic and Pacific across the thinnest stretch of the Isthmus of Tehuantepec. This initiative was intended to establish an alternative rail cargo route to the Panama Canal, intended to promote economic development in the area.
“We are going to rigorously clarify the reasons behind this incident,” affirmed the head of state.
The official confirmed that, of the approximately 250 individuals on board, another 98 were injured, with five of those in critical condition. The official added plans to visit Oaxaca to confer with those impacted.
Major Initiative of Former Government
The Interoceanic Train was a central infrastructure project of the former leader, whose term finished the year before. This rail line was a hallmark of his administration's strategic goals for the southeastern region.
Another massive railway undertaking from that time, a passenger and freight circuit around the Yucatán Peninsula, was also central to the wider plan to revitalize the economy of a relatively disadvantaged part of the country.
Building Management and Safety Concerns
The construction of both train projects was overseen by the armed forces, marking a significant growth of its responsibilities in civilian projects. They were completed at an accelerated rate, beating expectations to be at least partly opened before the end of that presidency.
However, this fast-paced schedule had simultaneously raised significant concerns over safety standards.
- Sunday's derailment was the third such incident on the Interoceanic Train this year.
- This includes an previous crash this month when a train struck a truck at a railroad crossing.
- The other major rail project has also had several non-deadly derailments.
Appeals for Audit and Pause
In the aftermath of the catastrophe, the chief of a key rival party urged an immediate halt in the building and running of all such projects.
This stoppage was proposed pending a full independent investigation. The party stated that the situation "requires immediate answers."
In reaction, the president insisted that the train had been operating in complete compliance with all safety requirements. Promises were given that the government would be "responsible" in both the development and operation of these strategic initiatives.